2015 Bond » Current Projects

Current Projects

Temple High School Fine Arts

Project: Construction of new band hall, HVAC upgrades, major upgrades to all department program spaces and parking/drive and site improvements.

Timeline:  October 2018 - December 2019,  Status: On time

Total Cost: $7 million

 

Lamar Middle School

Project:   Flip campus entry to the west with construction of a new library, kitchen/dining hall and administrative spaces. Major renovations to include electrical, mechanical and HVAC equipment, multiple classrooms, fine arts and athletic spaces, ADA upgrades to restrooms, parking/drive expansion and site improvements.

Timeline:  January 2019 - August 2020,  Status: On time

Total Cost: $16 million

 

Travis Middle School

Project: Construction of a new kitchen/dining hall, HVAC upgrades, ADA upgrades to restrooms, and major renovations to fine arts and athletic spaces

Timeline:  June 2018 - August 2019,  Status: On time

Total Cost: $9 million

 

Scott Elementary School

Project: Construction of classrooms, HVAC upgrades, ADA upgrades to restrooms, major renovations to the back classroom wing and parking/drive improvements.

Timeline:  June 2018 - August 2019,  Status: On time

Total Cost: $5.2 million

 

Western Hills Elementary School

Project: Construction of secured entry vestibule and improvements to the exterior entry area, HVAC upgrades, ADA upgrades to restrooms and major renovations to corridors and special education classrooms.

Timeline:  June 2018 - August 2019,  Status: On time

Total Cost: $4.8 million


Temple High School Special Education

Project: Major renovations to special education classrooms, offices and medical treatment spaces.

Timeline:  October 2018 - August 2019

Total Cost: $1.8 million


Temple High School Auto Technology

Project: Major renovations and addition to existing auto technology classrooms and shops, connect to new CTE facility and parking/drive improvements.

Timeline:  October 2018 - August 2019

Total Cost: $3 million